Oct 08, 2021 Leave a message

Operation steps of freeze dryer

1. Inspection before operation

① Check whether the circulating water pressure and compressed air pressure meet the requirements.

② Check whether the silicone oil level and the oil level and color of the vacuum pump are normal.

③ Check whether the color of compressor oil level, freon liquid level and moisture content display is within the normal range.

④ Check whether the computer program is normal.

⑤ Check whether the values of pressure gauge and thermometer are within the normal range.

⑥ Check that all valves are closed.

2. Loading

① The operator of the control post shall determine the procedures used on the control screen.

② Start the procedure of the loading stage of the lyophilizer.

③ Observe the freeze-drying curve and equipment operation diagram and refer to them accordingly.

④ Notify the sterile room when the inkstone temperature on the curve drops to 0 ℃.

Freeze dryer for dog food

3. Start

After the door of the aseptic room is closed, the foot position control operator shall start the freeze-drying procedure immediately after receiving the notice.

4. Operation

① Observe whether the freeze-drying curve is consistent with the set curve.

② Observe whether the equipment control system, vacuum system, heating system and refrigeration system are normal.

③ Observe whether all parts and door reading actions are correct in each stage of operation

④ The instrument shall indicate accurately and the equipment shall operate without abnormal sound

⑤ Observe that the oil level and liquid level shall meet the requirements, and the display of refrigerant moisture content shall be within the specified range.

5. Shutdown

When the drying pressure of phase II reaches the set requirements, the operation stops. At this time, the exhausted compressor needs to wait about 5min for operation protection before stopping.

6. Defrosting

① Determine the parameters of the chemical box program. Start the chemical box program after checking

② Observe whether all valves are opened and closed correctly during chemical beating. Whether the water temperature and quantity meet the requirements.

③ The water pump shall operate normally. There shall be no leakage at each connection point.

7. Unloading

① Start the cooling procedure, conduct the product array temperature, and stop the machine when the temperature drops to 15 ℃.

② Inform the sterile room to vent and discharge.


Send Inquiry

whatsapp

skype

E-mail

Inquiry